St Enoch upgrade

11 Dec 2013

St Enoch's busiest sub-way station is to be upgraded, creating a flagship city centre station.

The cost of upgrading one of Glasgow's busiest Subway stations will be £5.3million.

Tomorrow, Strathclyde Partnership for Transport is expected to agree the contract should be awarded to Graham Construction which has a base in the city.

The upgrade is part of the transport body's plan to carry out improvements to all 15 Subway stations in advance of driverless trains being introduced.

Hillhead, Partick and Ibrox stations are complete and work at Kelvinhall will be finished in time for the Commonwealth Games.

SPT say the works at St Enoch will take the same high quality approach as the previous stations creating an environment which is clean, efficient, more modern and passenger friendly.

Source: Evening Times - Cost of St Enochs upgrade is £5.3m